PENINGKATAN EFISIENSI PEMANFAATAN TENAGA KERJA MELALUI METODE RESOURCE LEVELING (STUDI KASUS PROYEK PEMBANGUNAN DERMAGA LANAL BIAK)

Authors

  • Isaiah Saron Imanuel Salu Universitas Pembangunan Indonesia Manado
  • Arnetha Sari Raintung Universitas Pembangunan Indonesia Manado
  • Stefani Switly Peginusa Politeknik Negeri Manado

DOI:

https://doi.org/10.17977/um071v30i22025p111-120

Keywords:

Resource Leveling, Labor Optimization, Microsoft Project

Abstract

The construction of a pier is a complex project, particularly in the management of human resources (HR). This study aims to evaluate the effectiveness of HR utilization in the Dermaga Lanal Biak pier construction project and optimize it through the application of the Resource Leveling method. This method is used to balance the distribution of labor and minimize workforce fluctuations during project execution, leading to a more efficient and controlled implementation. The analysis was conducted using Microsoft Project 2019, covering labor requirement calculations, critical path identification, and the application of Resource Leveling. The data analyzed included unit work plans, S-Curves, activity relationships, and labor coefficients based on the 2023 AHSP issued by the Indonesian Ministry of Public Works and Housing (PUPR). The results show that Resource Leveling successfully improved HR utilization efficiency by 25.31% without extending the project duration. This optimization is reflected in a more stable daily labor distribution and the effective use of float time. After analysis, the total human resource requirements were as follows: general workers 137.33 OH, carpenters 40 OH, masons 5.33 OH, foremen 6.53 OH, surveyors 1.75 OH, supervisors 6.67 OH, welders 23.93 OH, installers 0.02 OH, plumbers 1.61 OH, and steel workers 16.67 OH.

References

Atan, T., & Eren, E. (2018). Optimal project duration for resource leveling. European Journal of Operational Research, 266(2). https://doi.org/10.1016/j.ejor.2017.10.022

Gunaga, P. G., & George, G. (2022). Planning, Scheduling and Cost Estimation Of Villa Project Using Microsoft Project. International Journal for Research in Applied Science and Engineering Technology, 10(9), 1779–1792.

Inkiriwang, R. L., & Mangare, J. B. (2022). PERATAAN SUMBER DAYA TENAGA KERJA PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG MENGGUNAKAN MICROSOFT PROJECT. Jurnal Sipil Statik, 10(1), 47–56.

Kementerian PUPR. (2023). Peraturan Menteri PUPR Nomor: 8 Tahun 2023. Kementrian PUPR.

Leonard, A., Dundu, T. A. K. T., & Walangitan, D. R. O. (2019). Perataan Tenaga Kerja Dengan Menggunakan Microsoft Project Pada Proyek Rehabilitasi Puskesmas Minanga. Jurnal Sipil Statik, 7(10), 1261–1268.

Minarosi, A. A., Putra, I. N. D. P., & Nauli, A. R. (2023). ANALISIS RESOURCE LEVELING PADA TENAGA KERJA STUDI KASUS: PROYEK JLLB TAHAP2. Jurnal Ilmiah MITSU (Media Informasi Teknik Sipil Universitas Wiraraja), 11(1), 83–88.

Nangka, C. I. G., Sibi, M., & Mangare, J. B. (2018). Perataan Tenaga Kerja Pada Proyek Bangunan Dengan Menggunakan Microsoft Project (Studi Kasus: Proyek Pembangunan Terminal Akap Tangkoko Bitung). Jurnal Sipil Statik, 6(11), 867–874.

Nursuhud, D. D. (2021). Analisis Penggunaan Sumber Daya Manusia Dengan Metode Resource Levelling Studi Kasus Proyek Pembangunan Kost Supargiono Gondokusuman, Yogyakarta.

Peginusa, S. S., Tendean, C., & Raintung, A. S. (2025). Optimalisasi Sumber Daya Tenaga Kerja Proyek Pembangunan Hotel Amaris Manado Dengan Metode Resource Leveling. Jurnal Serambi Engineering, 10(2).

Puspitorini, I., & Bayu Adhi, S. (2024). Penerapan Resource Allocation dan Levelling tenaga Kerja Pada Proyek Konveksi. Jurnal Minfo Polgan, 12(2), 2728–2735. https://doi.org/10.33395/jmp.v12i2.13359

Ramadhan, M. Y. (2024). Perbandingan Penjadwalan Proyek dan Hasil Penerapan Resource Levelling pada Proyek Villa Munggu Menggunakan Microsoft Project. Politeknik Negeri Bali.

Retno, D. P., Astuti, A., & Tamimi, Z. (2018). Analisa Penggunaan Sumber Daya Manusia Dengan Metode Resource Leveling Pada Pelaksanaan Proyek Konstruksi (Studi Kasus: Proyek Pembangunan Ruang Kelas Baru Ponpes Daarun Nahdah Thawalib Bangkinang):

Analysis of the Use of Human Resources with Resource Lev. Jurnal Saintis, 18(1), 39–47.

Susilo, H. (2020). Penentuan Jumlah Tenaga Kerja Yang Optimal. JURNAL PILAR TEKNOLOGI Jurnal Ilmiah Ilmu Ilmu Teknik, 5(1).

Wasono, Ta, F. D., & Huda, M. N. (2019). Penentuan Percepatan Penyelesaian Proyek Pada Metode Jalur Kritis dengan Program Crash. Jurnal Eksponensial, 10(1), 89–94.

Willyanti, N. A. W. (2024). Analisis Perencanaan Tenaga Kerja menggunakan Metode Resource Leveling pada Proyek Pembangunan Gedung Apartment Sanur. Politeknik Negeri Bali.

YAHYA, A. R. (2022). Analisis Kebutuhan Tenaga Kerja Dengan Metode Resource Levelling (Analysis Of Labor Requirements Using The Resource Levelling Method)(Studi Kasus: Proyek Pembangunan Gereja Katolik Santa Maria Penolong Abadi, Samarinda, Kalimantan Timur).